SH 15 — DISMANTLING
89 unique item codes, preserving 92 analysed item variants from the source workbook.
Items in SH 15
- 15.1Demolishing lime concrete manually/ by mechanical means and disposal of material within 50 metres lead as per…₹851.50
- 15.2.1Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per…₹2,434.25
- 15.2.2Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per…₹1,503.60
- 15.3Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable…2 variants · ₹3,551.25
- 15.4Demolishing R.B. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable…₹3,177.25
- 15.5Extra for cutting reinforcement bars manually/ by mechanical means in R.C.C. or R.B. work (Payment shall be made on…2 variants · ₹1,147.20
- 15.6Extra for scrapping, cleaning and straightening reinforcement from R.C.C. or R.B. work.2 variants · ₹9.05
- 15.7.1Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of…₹704.90
- 15.7.2Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of…₹1,783.35
- 15.7.3Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of…₹851.50
- 15.7.4Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of…₹2,060.20
- 15.8.1Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks…₹4,658.45
- 15.8.2Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks…₹5,355.30
- 15.8.3Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks…₹6,700.80
- 15.9.1Demolishing stone rubble masonry manually/ by mechanical means including stacking of serviceable material and disposal…₹1,158.10
- 15.9.2Demolishing stone rubble masonry manually/ by mechanical means including stacking of serviceable material and disposal…₹2,458.95
- 15.10.1In lime mortar₹1,464.25
- 15.10.2In cement mortar₹2,877.75
- 15.11.1Removing mortar from and cleaning stones and concrete articles (net quantity of stacks of cleaned materials will be…₹478.55
- 15.11.2Removing mortar from and cleaning stones and concrete articles (net quantity of stacks of cleaned materials will be…₹689.20
- 15.12.1Dismantling doors, windows and clerestory windows (steel or wood) shutter including chowkhats, architrave, holdfasts…₹367.20
- 15.12.2Dismantling doors, windows and clerestory windows (steel or wood) shutter including chowkhats, architrave, holdfasts…₹502.75
- 15.13.1Taking out doors, windows and clerestory window shutters (steel or wood) including stacking within 50 metres lead : Of…₹143.50
- 15.13.2Taking out doors, windows and clerestory window shutters (steel or wood) including stacking within 50 metres lead : Of…₹188.90
- 15.14.1Dismantling wood work in frames, trusses, purlins and rafters up to 10 metres span and 5 metres height including…₹4,459.10
- 15.14.2Dismantling wood work in frames, trusses, purlins and rafters up to 10 metres span and 5 metres height including…₹17.85
- 15.15.1Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional span of one metre or part…₹589.55
- 15.15.2Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional span of one metre or part…₹1.65
- 15.16.1Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional height of one metre or part…₹857.00
- 15.16.2Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional height of one metre or part…₹3.40
- 15.17.1Dismantling steel work in single sections including dismembering and stacking within 50 metres lead in: R.S. Joists₹3.40
- 15.17.2Dismantling steel work in single sections including dismembering and stacking within 50 metres lead in: Channels,…₹2.30
- 15.18Dismantling steel work in built up sections in angles, tees, flats and channels including all gusset plates, bolts,…₹5.65
- 15.19Dismantling steel work manually/ by mechanical means in built up sections without dismembering and stacking within 50…₹3.85
- 15.2Extra for dismantling trusses, rafters, purlins etc. of steel work for every additional span of one metre or part…₹0.85
- 15.21Extra for dismantling trusses, rafters, purlins etc. of steel work for every additional height of one metre or part…₹0.85
- 15.22Extra for marking of structural steel work required to be re-erected.₹4.65
- 15.23.1Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres lead. For…₹73.40
- 15.23.2Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres lead. For…₹113.35
- 15.24Demolishing dry brick pitching in floors, drains etc. including stacking of serviceable material and disposal of…₹1,317.65
- 15.25Dismantling stone slab flooring laid in cement mortar including stacking of serviceable material and disposal of…₹266.45
- 15.26Demolishing brick tile covering in terracing including stacking of serviceable material and disposal of unserviceable…₹105.35
- 15.27Demolishing mud phaska in terracing and disposal of material within 50 metres lead.₹914.30
- 15.28.1Dismantling roofing including ridges, hips, valleys and gutters etc., and stacking the material within 50 metres lead…₹164.95
- 15.28.2Dismantling roofing including ridges, hips, valleys and gutters etc., and stacking the material within 50 metres lead…₹77.30
- 15.29Dismantling stone slab roofing over wooden karries or R.C.C. battens (dismantling karries and battens to be paid for…₹2,664.65
- 15.31Dismantling tiled roofing with battens, boarding etc. complete including stacking of serviceable material and disposal…₹209.90
- 15.32Demolishing thatch roofing including mats, bamboo, jaffari etc. complete including stacking of serviceable material…₹57.70
- 15.33Dismantling wooden ballies in posts and struts including stacking within 50metres lead.₹20.95
- 15.34.1Dismantling and stacking within 50 metres lead, fencing posts or struts including all earth work and dismantling of…₹230.90
- 15.34.2Dismantling and stacking within 50 metres lead, fencing posts or struts including all earth work and dismantling of…₹243.30
- 15.35Cutting ballies or wooden posts of fencing at the point of projection above the concrete or ground and stacking the…₹13.45
- 15.36Dismantling barbed wire or flexible wire rope in fencing including making rolls and stacking within 50 metres lead.₹36.80
- 15.37Dismantling wooden trellis work excluding frames but including stacking the serviceable material within 50 metres lead.₹64.85
- 15.38Dismantling expanded metal or I.R.C. fabrics with necessary battens and beading including stacking the serviceable…₹75.80
- 15.39.1Dismantling wooden boardings in lining of walls and partitions, excluding supporting members but including stacking…₹61.00
- 15.39.2Dismantling wooden boardings in lining of walls and partitions, excluding supporting members but including stacking…₹77.75
- 15.39.3Dismantling wooden boardings in lining of walls and partitions, excluding supporting members but including stacking…₹90.35
- 15.40.1Thickness up to 40 mm₹289.30
- 15.40.2Thickness above 40 mm up to 75 mm₹433.55
- 15.41Dismantling cement asbestos or other hard board ceiling or partition walls including stacking of serviceable materials…₹56.35
- 15.42.1Dismantling C.I. or asbestos rain water pipe with fittings and clamps including stacking the material within 50 metres…₹75.70
- 15.42.2Dismantling C.I. or asbestos rain water pipe with fittings and clamps including stacking the material within 50 metres…₹78.00
- 15.42.3Dismantling C.I. or asbestos rain water pipe with fittings and clamps including stacking the material within 50 metres…₹80.25
- 15.43.1Dismantling manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable…₹217.45
- 15.43.2Dismantling manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable…₹428.50
- 15.44.1Dismantling G.I. pipes (external work) including excavation and refilling trenches after taking out the pipes,…₹149.80
- 15.44.2Dismantling G.I. pipes (external work) including excavation and refilling trenches after taking out the pipes,…₹161.40
- 15.45.1Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical…₹332.40
- 15.45.2Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical…₹456.65
- 15.45.3Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical…₹614.30
- 15.46.1Dismantling steel cylinder R.C. pipes including excavation and refilling trenches after taking out the pipes,…₹695.25
- 15.46.2Dismantling steel cylinder R.C. pipes including excavation and refilling trenches after taking out the pipes,…₹1,752.45
- 15.47.1Dismantling asbestos cement pressure pipes including excavation and refilling trenches after taking out the pipes…₹332.15
- 15.47.2Dismantling asbestos cement pressure pipes including excavation and refilling trenches after taking out the pipes…₹403.05
- 15.48Taking out C.I. cover with frame from R.C.C. top slab of manholes of various sizes including demolishing of R.C.C.…₹697.40
- 15.49Taking out C.I. cover with frame from R.C.C. top slab of inspection chambers of various sizes including demolishing of…₹406.75
- 15.51Dismantling of road gully chamber of various sizes including C.I. grating with frame including stacking of useful…₹958.75
- 15.52Dismantling of flushing cistern of all types (C.I./PVC/Vitrious China) including stacking of useful materials near the…₹112.05
- 15.53.1Dismantling of C.I. sluice valve including stacking of useful materials within a lead of 50 metres Up to 150 mm diameter₹319.50
- 15.53.2Dismantling of C.I. sluice valve including stacking of useful materials within a lead of 50 metres Above 150 mm diameter₹1,184.15
- 15.54Dismantling of spindle fire hydrant including stacking of useful materials within 50 metres lead.₹726.35
- 15.55.1Dismantling of cement concrete platform along with curtain walls and base concrete etc. including stacking of useful…₹1,104.05
- 15.55.2Dismantling of cement concrete platform along with curtain walls and base concrete etc. including stacking of useful…₹1,693.35
- 15.55.3Dismantling of cement concrete platform along with curtain walls and base concrete etc. including stacking of useful…₹2,396.95
- 15.56Dismantling old plaster or skirting raking out joints and cleaning the surface for plaster including disposal of…₹54.65
- 15.57Dismantling aluminium/ Gypsum partitions, doors, windows, fixed glazing and false ceiling including disposal of…₹56.35
- 15.58Demolishing R.C.C. work by mechanical means and stockpiling at designated locations and disposal of dismantled…₹2,818.90
- 15.59Dismantling of flexible pavement (bituminous courses) by mechanical means and disposal of dismantled material up to a…₹420.80