DSR 2023 · SH 15 · DISMANTLING

CPWD DSR item 15.8.3 rate analysis

Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured): From brick work in cement mortar

Published rate₹6,700.80DSR 2023
Rate analysis

Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured):

DSR rate₹6,700.80as per item analysis

From brick work in cement mortar

Item code
15.8.3
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
211

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 1000 Nos
LABOUR
0114 Beldar day 3.5 ₹736.00 ₹2,576.00
0115 Coolie day 1.5 ₹736.00 ₹1,104.00
0124 Mason 2nd class day 1.24 ₹816.00 ₹1,011.84
9999 Sundries L.S. 8.06 ₹2.27 ₹18.30

Rate build-up

TOTAL ₹4,710.14
Add 1 % Water charges on "W" ₹47.10
TOTAL ₹4,757.24
Add GST on "X" (multiplying factor 0.2127) ₹1,011.86
TOTAL ₹5,769.10
Add 15% CPOH on "Y" ₹865.37
TOTAL ₹6,634.47
Add Cess @ 1% on "Z" ₹66.34
Cost of 1000 Nos ₹6,700.81
Say ₹6,700.80

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook