DSR 2023 · SH 15 · DISMANTLING

CPWD DSR item 15.9.1 rate analysis

Demolishing stone rubble masonry manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge : In lime mortar

Published rate₹1,158.10DSR 2023
Rate analysis

Demolishing stone rubble masonry manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge :

DSR rate₹1,158.10as per item analysis

In lime mortar

Item code
15.9.1
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
269

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 1 cum
LABOUR
0114 Beldar day 0.61 ₹736.00 ₹448.96
0115 Coolie day 0.49 ₹736.00 ₹360.64
9999 Sundries L.S. 1.95 ₹2.27 ₹4.43

Rate build-up

TOTAL ₹814.03
Add 1 % Water charges on "W" ₹8.14
TOTAL ₹822.17
Add GST on "X" (multiplying factor 0.2127) ₹174.88
TOTAL ₹997.05
Add 15% CPOH on "Y" ₹149.56
TOTAL ₹1,146.61
Add Cess @ 1% on "Z" ₹11.47
Cost of 1.00 cum ₹1,158.08
Say ₹1,158.10

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook