Rate analysis
Demolishing stone rubble masonry manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge :
DSR rate₹2,458.95as per item analysis
In cement mortar
- Item code
- 15.9.2
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 269
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 1 cum | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 1.3 | ₹736.00 | ₹956.80 |
| 0115 | Coolie | day | 1.04 | ₹736.00 | ₹765.44 |
| 9999 | Sundries | L.S. | 2.73 | ₹2.27 | ₹6.20 |
Rate build-up
| TOTAL | ₹1,728.44 |
| Add 1 % Water charges on "W" | ₹17.28 |
| TOTAL | ₹1,745.72 |
| Add GST on "X" (multiplying factor 0.2127) | ₹371.31 |
| TOTAL | ₹2,117.03 |
| Add 15% CPOH on "Y" | ₹317.55 |
| TOTAL | ₹2,434.58 |
| Add Cess @ 1% on "Z" | ₹24.35 |
| Cost of 1.00 cum | ₹2,458.93 |
| Say | ₹2,458.95 |