Rate analysis
Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional height of one metre or part thereof beyond 5 metres :
DSR rate₹3.40as per item analysis
Of sectional area below 40 square centimetres
- Item code
- 15.16.2
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 534
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 10 metre for every additional height of 1 metre | |||||
| LABOUR | |||||
| 0103 | Blacksmith 2nd class | day | 0.01 | ₹816.00 | ₹8.16 |
| 0114 | Beldar | day | 0.02 | ₹736.00 | ₹14.72 |
| 9999 | Sundries | L.S. | 0.39 | ₹2.27 | ₹0.89 |
Rate build-up
| TOTAL | ₹23.77 |
| Add 1 % Water charges on "W" | ₹0.24 |
| TOTAL | ₹24.01 |
| Add GST on "X" (multiplying factor 0.2127) | ₹5.11 |
| TOTAL | ₹29.12 |
| Add 15% CPOH on "Y" | ₹4.37 |
| TOTAL | ₹33.49 |
| Add Cess @ 1% on "Z" | ₹0.33 |
| Cost of 10.00 metre per metre height | ₹33.82 |
| Cost of 1.00 metre per metre height | ₹3.38 |
| Say | ₹3.40 |