DSR 2023 · SH 15 · DISMANTLING

CPWD DSR item 15.17.1 rate analysis

Dismantling steel work in single sections including dismembering and stacking within 50 metres lead in: R.S. Joists

Published rate₹3.40DSR 2023
Rate analysis

Dismantling steel work in single sections including dismembering and stacking within 50 metres lead in:

DSR rate₹3.40as per item analysis

R.S. Joists

Item code
15.17.1
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
572

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 1 quintal
LABOUR
0103 Blacksmith 2nd class day 0.05 ₹816.00 ₹40.80
0100 Bandhani day 0.1 ₹816.00 ₹81.60
0114 Beldar day 0.15 ₹736.00 ₹110.40
9999 Sundries L.S. 2.73 ₹2.27 ₹6.20

Rate build-up

TOTAL ₹239.00
Add 1 % Water charges on "W" ₹2.39
TOTAL ₹241.39
Add GST on "X" (multiplying factor 0.2127) ₹51.34
TOTAL ₹292.73
Add 15% CPOH on "Y" ₹43.91
TOTAL ₹336.64
Add Cess @ 1% on "Z" ₹3.37
Cost of 1.00 quintal ₹340.01
Cost of 1.00 kg ₹3.40
Say ₹3.40

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook