DSR 2023 · SH 15 · DISMANTLING

CPWD DSR item 15.17.2 rate analysis

Dismantling steel work in single sections including dismembering and stacking within 50 metres lead in: Channels, angles, tees and flats

Published rate₹2.30DSR 2023
Rate analysis

Dismantling steel work in single sections including dismembering and stacking within 50 metres lead in:

DSR rate₹2.30as per item analysis

Channels, angles, tees and flats

Item code
15.17.2
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
572

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 1 quintal
LABOUR
0103 Blacksmith 2nd class day 0.05 ₹816.00 ₹40.80
0100 Bandhani day 0.05 ₹816.00 ₹40.80
0114 Beldar day 0.1 ₹736.00 ₹73.60
9999 Sundries L.S. 2.73 ₹2.27 ₹6.20

Rate build-up

TOTAL ₹161.40
Add 1 % Water charges on "W" ₹1.61
TOTAL ₹163.01
Add GST on "X" (multiplying factor 0.2127) ₹34.67
TOTAL ₹197.68
Add 15% CPOH on "Y" ₹29.65
TOTAL ₹227.33
Add Cess @ 1% on "Z" ₹2.27
Cost of 1.00 quintal ₹229.60
Cost of 1.00 kg ₹2.30
Say ₹2.30

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook