Rate analysis
Dismantling steel work in built up sections in angles, tees, flats and channels including all gusset plates, bolts, nuts, cutting rivets, welding etc. including dismembering and stacking within 50 metres lead.
DSR rate₹5.65as per item analysis
- Item code
- 15.18
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 613
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 1 quintal | |||||
| LABOUR | |||||
| 0103 | Blacksmith 2nd class | day | 0.15 | ₹816.00 | ₹122.40 |
| 0100 | Bandhani | day | 0.1 | ₹816.00 | ₹81.60 |
| 0114 | Beldar | day | 0.25 | ₹736.00 | ₹184.00 |
| 9999 | Sundries | L.S. | 4.16 | ₹2.27 | ₹9.44 |
Rate build-up
| TOTAL | ₹397.44 |
| Add 1 % Water charges on "W" | ₹3.97 |
| TOTAL | ₹401.41 |
| Add GST on "X" (multiplying factor 0.2127) | ₹85.38 |
| TOTAL | ₹486.79 |
| Add 15% CPOH on "Y" | ₹73.02 |
| TOTAL | ₹559.81 |
| Add Cess @ 1% on "Z" | ₹5.60 |
| Cost of 1.00 quintal | ₹565.41 |
| Cost of 1.00 kg | ₹5.65 |
| Say | ₹5.65 |