Rate analysis
Demolishing R.C.C. work by mechanical means and stockpiling at designated locations and disposal of dismantled materials up to a lead of 1 kilometre, stacking serviceable and unserviceable material separately including cutting reinforcement bars.
DSR rate₹2,818.90per cum
- Item code
- 15.58
- Sub-head
- SH 15 · DISMANTLING
- Unit
- cum
- Source row
- 1866
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum | |||||
| LABOUR | |||||
| 0128 | Mate | day | 0.03 | ₹816.00 | ₹24.48 |
| Labour for operating pneumatic tools | |||||
| 0139 | Skilled Beldar (for floor rubbing etc.) | day | 0.5 | ₹816.00 | ₹408.00 |
| 0114 | Beldar | day | 0.5 | ₹736.00 | ₹368.00 |
| Labour for cutting reinforcement bars. | |||||
| 0103 | Blacksmith 2nd class | day | 0.5 | ₹816.00 | ₹408.00 |
| 0114 | Beldar | day | 0.5 | ₹736.00 | ₹368.00 |
| MACHINERY | |||||
| 0040 | Air compressor 250 cfm with two leads for pneumatic cutters/ hammers. | day | 0.125 | ₹1,800.00 | ₹225.00 |
| 0039 | Tractor with trolley . | day | 0.05 | ₹1,350.00 | ₹67.50 |
| 0041 | Joint cutting machine with 2-3 blades | day | 0.125 | ₹900.00 | ₹112.50 |
Rate build-up
| TOTAL | ₹1,981.48 |
| Add 1 % Water charges on "W" | ₹19.81 |
| TOTAL | ₹2,001.29 |
| Add GST on "X" (multiplying factor 0.2127) | ₹425.67 |
| TOTAL | ₹2,426.96 |
| Add 15% CPOH on "Y" | ₹364.04 |
| TOTAL | ₹2,791.00 |
| Add Cess @ 1% on "Z" | ₹27.91 |
| Cost of 1 cum | ₹2,818.91 |
| Say | ₹2,818.90 |