DSR 2023 · SH 15 · DISMANTLING

CPWD DSR item 15.59 rate analysis

Dismantling of flexible pavement (bituminous courses) by mechanical means and disposal of dismantled material up to a lead of 1 kilometre, as per direction of Engineer-in-charge.

Published rate₹420.80per cum
Rate analysis

Dismantling of flexible pavement (bituminous courses) by mechanical means and disposal of dismantled material up to a lead of 1 kilometre, as per direction of Engineer-in-charge.

DSR rate₹420.80per cum
Item code
15.59
Sub-head
SH 15 · DISMANTLING
Unit
cum
Source row
1892

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 cum
LABOUR
0128 Mate day 0.1 ₹816.00 ₹81.60
0114 Beldar day 3 ₹736.00 ₹2,208.00
MACHINERY
0039 Tractor with trolley . day 0.475 ₹1,350.00 ₹641.25
0038 Tractor with ripper attachment. day 0.02 ₹1,350.00 ₹27.00

Rate build-up

TOTAL ₹2,957.85
Add 1 % Water charges on "W" ₹29.58
TOTAL ₹2,987.43
Add GST on "X" (multiplying factor 0.2127) ₹635.43
TOTAL ₹3,622.86
Add 15% CPOH on "Y" ₹543.43
TOTAL ₹4,166.29
Add Cess @ 1% on "Z" ₹41.66
Cost of 10 cum ₹4,207.95
Cost of 1 cum ₹420.80
Say ₹420.80