DSR 2023 · SH 15 · DISMANTLING

CPWD DSR item 15.14.1 rate analysis

Dismantling wood work in frames, trusses, purlins and rafters up to 10 metres span and 5 metres height including stacking the material within 50 metres lead : Of sectional area 40 square centimetres and above

Published rate₹4,459.10DSR 2023
Rate analysis

Dismantling wood work in frames, trusses, purlins and rafters up to 10 metres span and 5 metres height including stacking the material within 50 metres lead :

DSR rate₹4,459.10as per item analysis

Of sectional area 40 square centimetres and above

Item code
15.14.1
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
458

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 1 cum
LABOUR
0112 Carpenter 2nd class day 2 ₹816.00 ₹1,632.00
0114 Beldar day 2 ₹736.00 ₹1,472.00
9999 Sundries L.S. 13.39 ₹2.27 ₹30.40

Rate build-up

TOTAL ₹3,134.40
Add 1 % Water charges on "W" ₹31.34
TOTAL ₹3,165.74
Add GST on "X" (multiplying factor 0.2127) ₹673.35
TOTAL ₹3,839.09
Add 15% CPOH on "Y" ₹575.86
TOTAL ₹4,414.95
Add Cess @ 1% on "Z" ₹44.15
Cost of 1.00 cum ₹4,459.10
Say ₹4,459.10

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook