Rate analysis
Dismantling wood work in frames, trusses, purlins and rafters up to 10 metres span and 5 metres height including stacking the material within 50 metres lead :
DSR rate₹4,459.10as per item analysis
Of sectional area 40 square centimetres and above
- Item code
- 15.14.1
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 458
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 1 cum | |||||
| LABOUR | |||||
| 0112 | Carpenter 2nd class | day | 2 | ₹816.00 | ₹1,632.00 |
| 0114 | Beldar | day | 2 | ₹736.00 | ₹1,472.00 |
| 9999 | Sundries | L.S. | 13.39 | ₹2.27 | ₹30.40 |
Rate build-up
| TOTAL | ₹3,134.40 |
| Add 1 % Water charges on "W" | ₹31.34 |
| TOTAL | ₹3,165.74 |
| Add GST on "X" (multiplying factor 0.2127) | ₹673.35 |
| TOTAL | ₹3,839.09 |
| Add 15% CPOH on "Y" | ₹575.86 |
| TOTAL | ₹4,414.95 |
| Add Cess @ 1% on "Z" | ₹44.15 |
| Cost of 1.00 cum | ₹4,459.10 |
| Say | ₹4,459.10 |