DSR 2023 · SH 15 · DISMANTLING

CPWD DSR item 15.14.2 rate analysis

Dismantling wood work in frames, trusses, purlins and rafters up to 10 metres span and 5 metres height including stacking the material within 50 metres lead : Of sectional area below 40 square centimetres

Published rate₹17.85DSR 2023
Rate analysis

Dismantling wood work in frames, trusses, purlins and rafters up to 10 metres span and 5 metres height including stacking the material within 50 metres lead :

DSR rate₹17.85as per item analysis

Of sectional area below 40 square centimetres

Item code
15.14.2
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
458

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 10 metre
LABOUR
0112 Carpenter 2nd class day 0.08 ₹816.00 ₹65.28
0114 Beldar day 0.08 ₹736.00 ₹58.88
9999 Sundries L.S. 0.52 ₹2.27 ₹1.18

Rate build-up

TOTAL ₹125.34
Add 1 % Water charges on "W" ₹1.25
TOTAL ₹126.59
Add GST on "X" (multiplying factor 0.2127) ₹26.93
TOTAL ₹153.52
Add 15% CPOH on "Y" ₹23.03
TOTAL ₹176.55
Add Cess @ 1% on "Z" ₹1.77
Cost of 10.00 metre ₹178.32
Cost of 1.00 metre ₹17.83
Say ₹17.85