CPWD DSR item 15.15.1 rate analysis

Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional span of one metre or part thereof beyond 10 metres : Of sectional area 40 square centimetres and above

Published rate₹589.55DSR 2023
Rate analysis

Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional span of one metre or part thereof beyond 10 metres :

DSR rate₹589.55as per item analysis

Of sectional area 40 square centimetres and above

Item code
15.15.1
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
496

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 1cum for every additional span of 1 metre
LABOUR
0103 Blacksmith 2nd class day 0.2 ₹816.00 ₹163.20
0114 Beldar day 0.3 ₹736.00 ₹220.80
9999 Sundries L.S. 13.39 ₹2.27 ₹30.40

Rate build-up

TOTAL ₹414.40
Add 1 % Water charges on "W" ₹4.14
TOTAL ₹418.54
Add GST on "X" (multiplying factor 0.2127) ₹89.02
TOTAL ₹507.56
Add 15% CPOH on "Y" ₹76.13
TOTAL ₹583.69
Add Cess @ 1% on "Z" ₹5.84
Cost of 1.00 cum per metre span ₹589.53
Say ₹589.55