Rate analysis
Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional span of one metre or part thereof beyond 10 metres :
DSR rate₹1.65as per item analysis
Of sectional area below 40 square centimetres
- Item code
- 15.15.2
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 496
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 10 metre for every additional span of 1 metre | |||||
| LABOUR | |||||
| 0103 | Blacksmith 2nd class | day | 0.006 | ₹816.00 | ₹4.90 |
| 0114 | Beldar | day | 0.008 | ₹736.00 | ₹5.89 |
| 9999 | Sundries | L.S. | 0.39 | ₹2.27 | ₹0.89 |
Rate build-up
| TOTAL | ₹11.68 |
| Add 1 % Water charges on "W" | ₹0.12 |
| TOTAL | ₹11.80 |
| Add GST on "X" (multiplying factor 0.2127) | ₹2.51 |
| TOTAL | ₹14.31 |
| Add 15% CPOH on "Y" | ₹2.15 |
| TOTAL | ₹16.46 |
| Add Cess @ 1% on "Z" | ₹0.16 |
| Cost of 10.00 metre per metre span | ₹16.62 |
| Cost of 1.00 metre per metre span | ₹1.66 |
| Say | ₹1.65 |