DSR 2023 · SH 15 · DISMANTLING

CPWD DSR item 15.47.1 rate analysis

Dismantling asbestos cement pressure pipes including excavation and refilling trenches after taking out the pipes manually/ by mechanical means and stacking the pipes within 50 metres lead as per direction of Engineer-in-charge : Up to 150 mm diameter

Published rate₹332.15DSR 2023
Rate analysis

Dismantling asbestos cement pressure pipes including excavation and refilling trenches after taking out the pipes manually/ by mechanical means and stacking the pipes within 50 metres lead as per direction of Engineer-in-charge :

DSR rate₹332.15as per item analysis

Up to 150 mm diameter

Item code
15.47.1
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
1479

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 10 metre or 11 nos joints
Earth work in excavation for dismantling pipes including refilling of excavated earth
10.00x0.55x0.75 m =4.125cum
Deduct for pipes of average 100 mm dia
=1x10x(22/7)/4x(0.118)x(0.118) =0.109cum
Total=4.016cum
LABOUR
0114 Beldar day 1.16 ₹736.00 ₹853.76
0115 Coolie day 1.19 ₹736.00 ₹875.84
0101 Bhisti day 0.07 ₹816.00 ₹57.12
0114 Beldar day 0.36 ₹736.00 ₹264.96
0115 Coolie day 0.38 ₹736.00 ₹279.68
9988 Carriage and sundries L.S. 1.56 ₹2.27 ₹3.54

Rate build-up

TOTAL ₹2,334.90
Add 1 % Water charges on "W" ₹23.35
TOTAL ₹2,358.25
Add GST on "X" (multiplying factor 0.2127) ₹501.60
TOTAL ₹2,859.85
Add 15% CPOH on "Y" ₹428.98
TOTAL ₹3,288.83
Add Cess @ 1% on "Z" ₹32.89
Cost of 10.00 metre ₹3,321.72
Cost of 1.00 metre ₹332.17
Say ₹332.15

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.