Rate analysis
Dismantling asbestos cement pressure pipes including excavation and refilling trenches after taking out the pipes manually/ by mechanical means and stacking the pipes within 50 metres lead as per direction of Engineer-in-charge :
DSR rate₹403.05as per item analysis
Above 150 mm diameter
- Item code
- 15.47.2
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 1479
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 10 metre or 11 nos joints | |||||
| Earth work in excavation for dismantling pipes including refilling of excavated earth | |||||
| 10.00x0.65x0.75 m =4.88cum | |||||
| Deduct for pipes of average 250 mm dia | |||||
| =1x10x(22/7)/4x(0.274)x(0.274) =0.590cum | |||||
| Total=4.29cum | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 1.24 | ₹736.00 | ₹912.64 |
| 0115 | Coolie | day | 1.28 | ₹736.00 | ₹942.08 |
| 0101 | Bhisti | day | 0.07 | ₹816.00 | ₹57.12 |
| 0114 | Beldar | day | 0.36 | ₹736.00 | ₹264.96 |
| 0115 | Coolie | day | 0.88 | ₹736.00 | ₹647.68 |
| 9988 | Carriage and sundries | L.S. | 3.77 | ₹2.27 | ₹8.56 |
Rate build-up
| TOTAL | ₹2,833.04 |
| Add 1 % Water charges on "W" | ₹28.33 |
| TOTAL | ₹2,861.37 |
| Add GST on "X" (multiplying factor 0.2127) | ₹608.61 |
| TOTAL | ₹3,469.98 |
| Add 15% CPOH on "Y" | ₹520.50 |
| TOTAL | ₹3,990.48 |
| Add Cess @ 1% on "Z" | ₹39.90 |
| Cost of 10.00 metre | ₹4,030.38 |
| Cost of 1.00 metre | ₹403.04 |
| Say | ₹403.05 |