Rate analysis
Taking out C.I. cover with frame from R.C.C. top slab of manholes of various sizes including demolishing of R.C.C. work manually/ by mechanical means and stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead as per direction of Engineer-in-charge.
DSR rate₹697.40as per item analysis
- Item code
- 15.48
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 1534
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 man hole | |||||
| Demolition of R.C.C. slab 1.3x1.2x0.15 m =0.234cum | |||||
| Less cover 0.61x0.455x0.15 m =0.042cum | |||||
| Net Quantity =0.192cum | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 0.5 | ₹736.00 | ₹368.00 |
| 0115 | Coolie | day | 0.14 | ₹736.00 | ₹103.04 |
| 9999 | Removel of C.I. Cover with frame including stacking | L.S. | 1.3 | ₹2.27 | ₹2.95 |
| 9999 | Sundries | L.S. | 7.15 | ₹2.27 | ₹16.23 |
Rate build-up
| TOTAL | ₹490.22 |
| Add 1 % Water charges on "W" | ₹4.90 |
| TOTAL | ₹495.12 |
| Add GST on "X" (multiplying factor 0.2127) | ₹105.31 |
| TOTAL | ₹600.43 |
| Add 15% CPOH on "Y" | ₹90.06 |
| TOTAL | ₹690.49 |
| Add Cess @ 1% on "Z" | ₹6.90 |
| Cost of each | ₹697.39 |
| Say | ₹697.40 |