CPWD DSR item 15.48 rate analysis

Taking out C.I. cover with frame from R.C.C. top slab of manholes of various sizes including demolishing of R.C.C. work manually/ by mechanical means and stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead as per direction of Engineer-in-charge.

Published rate₹697.40DSR 2023
Rate analysis

Taking out C.I. cover with frame from R.C.C. top slab of manholes of various sizes including demolishing of R.C.C. work manually/ by mechanical means and stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead as per direction of Engineer-in-charge.

DSR rate₹697.40as per item analysis
Item code
15.48
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
1534

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 man hole
Demolition of R.C.C. slab 1.3x1.2x0.15 m =0.234cum
Less cover 0.61x0.455x0.15 m =0.042cum
Net Quantity =0.192cum
LABOUR
0114 Beldar day 0.5 ₹736.00 ₹368.00
0115 Coolie day 0.14 ₹736.00 ₹103.04
9999 Removel of C.I. Cover with frame including stacking L.S. 1.3 ₹2.27 ₹2.95
9999 Sundries L.S. 7.15 ₹2.27 ₹16.23

Rate build-up

TOTAL ₹490.22
Add 1 % Water charges on "W" ₹4.90
TOTAL ₹495.12
Add GST on "X" (multiplying factor 0.2127) ₹105.31
TOTAL ₹600.43
Add 15% CPOH on "Y" ₹90.06
TOTAL ₹690.49
Add Cess @ 1% on "Z" ₹6.90
Cost of each ₹697.39
Say ₹697.40