DSR 2023 · SH 15 · DISMANTLING

CPWD DSR item 15.49 rate analysis

Taking out C.I. cover with frame from R.C.C. top slab of inspection chambers of various sizes including demolishing of R.C.C. work manually/ by mechanical means and stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead as per direction of Engineer-in-charge.

Published rate₹406.75DSR 2023
Rate analysis

Taking out C.I. cover with frame from R.C.C. top slab of inspection chambers of various sizes including demolishing of R.C.C. work manually/ by mechanical means and stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead as per direction of Engineer-in-charge.

DSR rate₹406.75as per item analysis
Item code
15.49
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
1556

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 1 man hole
Demolition of R.C.C. slab
1.1x0.9x0.15 m =0.148cum
Less cover 0.61x0.455x0.15 m =0.042cum
=0.106cum Say 0.11cum
LABOUR
0114 Beldar day 0.29 ₹736.00 ₹213.44
0115 Coolie day 0.08 ₹736.00 ₹58.88
9999 Removel of C.I. Cover with frame including stacking L.S. 0.65 ₹2.27 ₹1.48
9999 Sundries L.S. 5.33 ₹2.27 ₹12.10

Rate build-up

TOTAL ₹285.90
Add 1 % Water charges on "W" ₹2.86
TOTAL ₹288.76
Add GST on "X" (multiplying factor 0.2127) ₹61.42
TOTAL ₹350.18
Add 15% CPOH on "Y" ₹52.53
TOTAL ₹402.71
Add Cess @ 1% on "Z" ₹4.03
Cost of each ₹406.74