Rate analysis
Taking out C.I. cover with frame from R.C.C. top slab of inspection chambers of various sizes including demolishing of R.C.C. work manually/ by mechanical means and stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead as per direction of Engineer-in-charge.
DSR rate₹406.75as per item analysis
- Item code
- 15.49
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 1556
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 1 man hole | |||||
| Demolition of R.C.C. slab | |||||
| 1.1x0.9x0.15 m =0.148cum | |||||
| Less cover 0.61x0.455x0.15 m =0.042cum | |||||
| =0.106cum Say 0.11cum | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 0.29 | ₹736.00 | ₹213.44 |
| 0115 | Coolie | day | 0.08 | ₹736.00 | ₹58.88 |
| 9999 | Removel of C.I. Cover with frame including stacking | L.S. | 0.65 | ₹2.27 | ₹1.48 |
| 9999 | Sundries | L.S. | 5.33 | ₹2.27 | ₹12.10 |
Rate build-up
| TOTAL | ₹285.90 |
| Add 1 % Water charges on "W" | ₹2.86 |
| TOTAL | ₹288.76 |
| Add GST on "X" (multiplying factor 0.2127) | ₹61.42 |
| TOTAL | ₹350.18 |
| Add 15% CPOH on "Y" | ₹52.53 |
| TOTAL | ₹402.71 |
| Add Cess @ 1% on "Z" | ₹4.03 |
| Cost of each | ₹406.74 |
| Say | ₹406.75 |