DSR 2023 · SH 15 · DISMANTLING

CPWD DSR item 15.51 rate analysis

Dismantling of road gully chamber of various sizes including C.I. grating with frame including stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead including refilling the excavated gap.

Published rate₹958.75DSR 2023
Rate analysis

Dismantling of road gully chamber of various sizes including C.I. grating with frame including stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead including refilling the excavated gap.

DSR rate₹958.75as per item analysis
Item code
15.51
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
1615

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for one chamber
Dismantling cement concrete
a) 1:5:10 1.05x1.00x0.15m =0.16cum
Dismantling brick work in cement mortar
2.70x0.20x0.45m =0.24cum
Dismantling cement concrete
b) 1:2:4 2.70x0.20x0.15m =0.08cum
LABOUR
0114 Beldar day 0.14 ₹736.00 ₹103.04
0115 Coolie day 0.09 ₹736.00 ₹66.24
9999 Sundries L.S. 0.26 ₹2.27 ₹0.59
0114 Beldar day 0.25 ₹736.00 ₹184.00
0115 Coolie day 0.22 ₹736.00 ₹161.92
9999 Sundries L.S. 0.52 ₹2.27 ₹1.18
0114 Beldar day 0.13 ₹736.00 ₹95.68
0115 Coolie day 0.06 ₹736.00 ₹44.16
9999 Sundries for scaffolding etc L.S. 0.39 ₹2.27 ₹0.89
9999 Dismantling C.I. Grating L.S. 7.15 ₹2.27 ₹16.23

Rate build-up

TOTAL ₹673.93
Add 1 % Water charges on "W" ₹6.74
TOTAL ₹680.67
Add GST on "X" (multiplying factor 0.2127) ₹144.78
TOTAL ₹825.45
Add 15% CPOH on "Y" ₹123.82
TOTAL ₹949.27
Add Cess @ 1% on "Z" ₹9.49
Cost of each ₹958.76
Say ₹958.75