Rate analysis
Dismantling of flushing cistern of all types (C.I./PVC/Vitrious China) including stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead.
DSR rate₹112.05as per item analysis
- Item code
- 15.52
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 1646
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for each | |||||
| LABOUR | |||||
| 0117 | Fitter (grade 2) | day | 0.05 | ₹816.00 | ₹40.80 |
| 0114 | Beldar | day | 0.05 | ₹736.00 | ₹36.80 |
| 9999 | Sundries | L.S. | 0.52 | ₹2.27 | ₹1.18 |
Rate build-up
| TOTAL | ₹78.78 |
| Add 1 % Water charges on "W" | ₹0.79 |
| TOTAL | ₹79.57 |
| Add GST on "X" (multiplying factor 0.2127) | ₹16.92 |
| TOTAL | ₹96.49 |
| Add 15% CPOH on "Y" | ₹14.47 |
| TOTAL | ₹110.96 |
| Add Cess @ 1% on "Z" | ₹1.11 |
| Cost of each | ₹112.07 |
| Say | ₹112.05 |