Rate analysis
Dismantling steel cylinder R.C. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metres lead as per direction of Engineer-in-charge :
DSR rate₹1,752.45as per item analysis
Above 600 mm diameter
- Item code
- 15.46.2
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 1420
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 40.26 metre or 11 nos joints | |||||
| Earth work in excavation for dismantling pipes including refilling of excavated earth | |||||
| 1x40.26x1.30x1.65 m =86.36cum | |||||
| Deduct for pipes of average 900 mm dia | |||||
| =1x40.26x(22/7)/4x(1.00)x(1.00) =31.63cum | |||||
| Total=54.73cum | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 15.82 | ₹736.00 | ₹11,643.52 |
| 0115 | Coolie | day | 16.25 | ₹736.00 | ₹11,960.00 |
| 0101 | Bhisti | day | 0.93 | ₹816.00 | ₹758.88 |
| 0761 | Fuel wood | quintal | 3.08 | ₹550.00 | ₹1,694.00 |
| 0771 | Kerosene oil | litre | 5 | ₹50.00 | ₹250.00 |
| 0117 | Assistant Fitter or 2nd class Fitter | day | 10 | ₹816.00 | ₹8,160.00 |
| 0114 | Beldar | day | 20 | ₹736.00 | ₹14,720.00 |
| 9988 | Carriage and sundries | L.S. | 179.4 | ₹2.27 | ₹407.24 |
Rate build-up
| TOTAL | ₹49,593.64 |
| Add 1 % Water charges on "W" | ₹495.94 |
| TOTAL | ₹50,089.58 |
| Add GST on "X" (multiplying factor 0.2127) | ₹10,654.05 |
| TOTAL | ₹60,743.63 |
| Add 15% CPOH on "Y" | ₹9,111.54 |
| TOTAL | ₹69,855.17 |
| Add Cess @ 1% on "Z" | ₹698.55 |
| Cost of 40.26 metre | ₹70,553.72 |
| Cost of 1.00 metre | ₹1,752.45 |
| Say | ₹1,752.45 |