Rate analysis
Dismantling steel cylinder R.C. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metres lead as per direction of Engineer-in-charge :
DSR rate₹695.25as per item analysis
Up to 600 mm diameter
- Item code
- 15.46.1
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 1420
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 40.26 metre or 11 nos joints | |||||
| Earth work in excavation for dismantling pipes including refilling of excavated earth | |||||
| 1x40.26x1.30x1.65 m =86.36cum | |||||
| Deduct for pipes of average 450 mm dia | |||||
| =1x40.26x(22/7)/4x(0.48)x(0.48) =7.29cum | |||||
| Total=79.07cum | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 5.32 | ₹736.00 | ₹3,915.52 |
| 0115 | Coolie | day | 5.46 | ₹736.00 | ₹4,018.56 |
| 0101 | Bhisti | day | 0.31 | ₹816.00 | ₹252.96 |
| 0761 | Fuel wood | quintal | 1.4 | ₹550.00 | ₹770.00 |
| 0771 | Kerosene oil | litre | 2.27 | ₹50.00 | ₹113.50 |
| 0117 | Assistant Fitter or 2nd class Fitter | day | 2.25 | ₹816.00 | ₹1,836.00 |
| 0114 | Beldar | day | 11.5 | ₹736.00 | ₹8,464.00 |
| 9988 | Carriage and sundries | L.S. | 134.55 | ₹2.27 | ₹305.43 |
Rate build-up
| TOTAL | ₹19,675.97 |
| Add 1 % Water charges on "W" | ₹196.76 |
| TOTAL | ₹19,872.73 |
| Add GST on "X" (multiplying factor 0.2127) | ₹4,226.93 |
| TOTAL | ₹24,099.66 |
| Add 15% CPOH on "Y" | ₹3,614.95 |
| TOTAL | ₹27,714.61 |
| Add Cess @ 1% on "Z" | ₹277.15 |
| Cost of 40.26 metre | ₹27,991.76 |
| Cost of 1.00 metre | ₹695.27 |
| Say | ₹695.25 |