CPWD DSR item 15.27 rate analysis

Demolishing mud phaska in terracing and disposal of material within 50 metres lead.

Published rate₹914.30DSR 2023
Rate analysis

Demolishing mud phaska in terracing and disposal of material within 50 metres lead.

DSR rate₹914.30as per item analysis
Item code
15.27
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
806

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 1 cum
LABOUR
0114 Beldar day 0.25 ₹736.00 ₹184.00
0115 Coolie day 0.62 ₹736.00 ₹456.32
9999 Sundries L.S. 1.04 ₹2.27 ₹2.36

Rate build-up

TOTAL ₹642.68
Add 1 % Water charges on "W" ₹6.43
TOTAL ₹649.11
Add GST on "X" (multiplying factor 0.2127) ₹138.07
TOTAL ₹787.18
Add 15% CPOH on "Y" ₹118.08
TOTAL ₹905.26
Add Cess @ 1% on "Z" ₹9.05
Cost of 1.00 cum ₹914.31
Say ₹914.30