DSR 2023 · SH 15 · DISMANTLING

CPWD DSR item 15.26 rate analysis

Demolishing brick tile covering in terracing including stacking of serviceable material and disposal of unserviceable material within 50 metres lead.

Published rate₹105.35DSR 2023
Rate analysis

Demolishing brick tile covering in terracing including stacking of serviceable material and disposal of unserviceable material within 50 metres lead.

DSR rate₹105.35as per item analysis
Item code
15.26
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
786

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 10 sqm
LABOUR
0124 Mason 2nd class day 0.54 ₹816.00 ₹440.64
0114 Beldar day 0.16 ₹736.00 ₹117.76
0115 Coolie day 0.24 ₹736.00 ₹176.64
9999 Sundries L.S. 2.47 ₹2.27 ₹5.61

Rate build-up

TOTAL ₹740.65
Add 1 % Water charges on "W" ₹7.41
TOTAL ₹748.06
Add GST on "X" (multiplying factor 0.2127) ₹159.11
TOTAL ₹907.17
Add 15% CPOH on "Y" ₹136.08
TOTAL ₹1,043.25
Add Cess @ 1% on "Z" ₹10.43
Cost of 10.00 sqm ₹1,053.68
Cost of 1.00 sqm ₹105.37
Say ₹105.35

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.