Rate analysis
Dismantling manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge :
DSR rate₹428.50as per item analysis
bituminous road
- Item code
- 15.43.2
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 1251
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 36 sqm | |||||
| Consider a road 6 metres wide and 6 metres length wise 30 cm average depth =10.80 cubic metre | |||||
| LABOUR | |||||
| For cutting road taking out soiling and metalling including sorting and screening | |||||
| 0114 | Beldar | day | 9.6 | ₹736.00 | ₹7,065.60 |
| 0115 | Coolie | day | 4.8 | ₹736.00 | ₹3,532.80 |
| 9999 | Labour for stacking of serviceable material and disposal of unserviceable material within 50 metres lead | L.S. | 107.64 | ₹2.27 | ₹244.34 |
Rate build-up
| TOTAL | ₹10,842.74 |
| Add 1 % Water charges on "W" | ₹108.43 |
| TOTAL | ₹10,951.17 |
| Add GST on "X" (multiplying factor 0.2127) | ₹2,329.31 |
| TOTAL | ₹13,280.48 |
| Add 15% CPOH on "Y" | ₹1,992.07 |
| TOTAL | ₹15,272.55 |
| Add Cess @ 1% on "Z" | ₹152.73 |
| Cost of 36.00 sqm | ₹15,425.28 |
| Cost of 1.00 sqm | ₹428.48 |
| Say | ₹428.50 |