DSR 2023 · SH 15 · DISMANTLING

CPWD DSR item 15.43.1 rate analysis

Dismantling manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge : Water bound macadam road

Published rate₹217.45DSR 2023
Rate analysis

Dismantling manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge :

DSR rate₹217.45as per item analysis

Water bound macadam road

Item code
15.43.1
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
1251

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 36 sqm
Consider a road 6 metres wide and 6 metres length wise 25 cm average depth = 9.00 cubic metre
LABOUR
For cutting road taking out soiling and metalling including sorting and screening
0114 Beldar day 4.8 ₹736.00 ₹3,532.80
0115 Coolie day 2.4 ₹736.00 ₹1,766.40
9999 Labour for stacking of serviceable material and disposal of unserviceable material within 50 metres lead L.S. 89.7 ₹2.27 ₹203.62

Rate build-up

TOTAL ₹5,502.82
Add 1 % Water charges on "W" ₹55.03
TOTAL ₹5,557.85
Add GST on "X" (multiplying factor 0.2127) ₹1,182.15
TOTAL ₹6,740.00
Add 15% CPOH on "Y" ₹1,011.00
TOTAL ₹7,751.00
Add Cess @ 1% on "Z" ₹77.51
Cost of 36.00 sqm ₹7,828.51
Cost of 1.00 sqm ₹217.46
Say ₹217.45