Rate analysis
Dismantling wooden boardings in lining of walls and partitions, excluding supporting members but including stacking within 50 metres lead :
DSR rate₹77.75as per item analysis
Thickness above 10 mm up to 25 mm
- Item code
- 15.39.2
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 1072
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 10 sqm | |||||
| LABOUR | |||||
| 0112 | Carpenter 2nd class | day | 0.2 | ₹816.00 | ₹163.20 |
| 0114 | Beldar | day | 0.25 | ₹736.00 | ₹184.00 |
| 0115 | Coolie | day | 0.25 | ₹736.00 | ₹184.00 |
| 9999 | Sundries | L.S. | 6.76 | ₹2.27 | ₹15.35 |
Rate build-up
| TOTAL | ₹546.55 |
| Add 1 % Water charges on "W" | ₹5.47 |
| TOTAL | ₹552.02 |
| Add GST on "X" (multiplying factor 0.2127) | ₹117.41 |
| TOTAL | ₹669.43 |
| Add 15% CPOH on "Y" | ₹100.41 |
| TOTAL | ₹769.84 |
| Add Cess @ 1% on "Z" | ₹7.70 |
| Cost of 10.00 sqm | ₹777.54 |
| Cost of 1.00 sqm | ₹77.75 |
| Say | ₹77.75 |