Rate analysis
Dismantling wooden boardings in lining of walls and partitions, excluding supporting members but including stacking within 50 metres lead :
DSR rate₹61.00as per item analysis
Up to 10 mm thick
- Item code
- 15.39.1
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 1072
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 10 sqm | |||||
| LABOUR | |||||
| 0112 | Carpenter 2nd class | day | 0.15 | ₹816.00 | ₹122.40 |
| 0114 | Beldar | day | 0.2 | ₹736.00 | ₹147.20 |
| 0115 | Coolie | day | 0.2 | ₹736.00 | ₹147.20 |
| 9999 | Sundries | L.S. | 5.33 | ₹2.27 | ₹12.10 |
Rate build-up
| TOTAL | ₹428.90 |
| Add 1 % Water charges on "W" | ₹4.29 |
| TOTAL | ₹433.19 |
| Add GST on "X" (multiplying factor 0.2127) | ₹92.14 |
| TOTAL | ₹525.33 |
| Add 15% CPOH on "Y" | ₹78.80 |
| TOTAL | ₹604.13 |
| Add Cess @ 1% on "Z" | ₹6.04 |
| Cost of 10.00 sqm | ₹610.17 |
| Cost of 1.00 sqm | ₹61.02 |
| Say | ₹61.00 |