Rate analysis
Dismantling expanded metal or I.R.C. fabrics with necessary battens and beading including stacking the serviceable material within 50 metres lead.
DSR rate₹75.80as per item analysis
- Item code
- 15.38
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 1052
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 10 sqm | |||||
| LABOUR | |||||
| 0112 | Carpenter 2nd class | day | 0.1 | ₹816.00 | ₹81.60 |
| 0114 | Beldar | day | 0.4 | ₹736.00 | ₹294.40 |
| 0115 | Coolie | day | 0.2 | ₹736.00 | ₹147.20 |
| 9999 | Sundries | L.S. | 4.16 | ₹2.27 | ₹9.44 |
Rate build-up
| TOTAL | ₹532.64 |
| Add 1 % Water charges on "W" | ₹5.33 |
| TOTAL | ₹537.97 |
| Add GST on "X" (multiplying factor 0.2127) | ₹114.43 |
| TOTAL | ₹652.40 |
| Add 15% CPOH on "Y" | ₹97.86 |
| TOTAL | ₹750.26 |
| Add Cess @ 1% on "Z" | ₹7.50 |
| Cost of 10.00 sqm | ₹757.76 |
| Cost of 1.00 sqm | ₹75.78 |
| Say | ₹75.80 |