Rate analysis
Dismantling wooden trellis work excluding frames but including stacking the serviceable material within 50 metres lead.
DSR rate₹64.85as per item analysis
- Item code
- 15.37
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 1032
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 10 sqm | |||||
| LABOUR | |||||
| 0124 | Mason 2nd class | day | 0.1 | ₹816.00 | ₹81.60 |
| 0114 | Beldar | day | 0.25 | ₹736.00 | ₹184.00 |
| 0115 | Coolie | day | 0.25 | ₹736.00 | ₹184.00 |
| 9999 | Sundries | L.S. | 2.73 | ₹2.27 | ₹6.20 |
Rate build-up
| TOTAL | ₹455.80 |
| Add 1 % Water charges on "W" | ₹4.56 |
| TOTAL | ₹460.36 |
| Add GST on "X" (multiplying factor 0.2127) | ₹97.92 |
| TOTAL | ₹558.28 |
| Add 15% CPOH on "Y" | ₹83.74 |
| TOTAL | ₹642.02 |
| Add Cess @ 1% on "Z" | ₹6.42 |
| Cost of 10.00 sqm | ₹648.44 |
| Cost of 1.00 sqm | ₹64.84 |
| Say | ₹64.85 |