Rate analysis
Dismantling barbed wire or flexible wire rope in fencing including making rolls and stacking within 50 metres lead.
DSR rate₹36.80as per item analysis
- Item code
- 15.36
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 1014
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 1 quintal | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 3.5 | ₹736.00 | ₹2,576.00 |
| 9999 | Sundries | L.S. | 5.33 | ₹2.27 | ₹12.10 |
Rate build-up
| TOTAL | ₹2,588.10 |
| Add 1 % Water charges on "W" | ₹25.88 |
| TOTAL | ₹2,613.98 |
| Add GST on "X" (multiplying factor 0.2127) | ₹555.99 |
| TOTAL | ₹3,169.97 |
| Add 15% CPOH on "Y" | ₹475.50 |
| TOTAL | ₹3,645.47 |
| Add Cess @ 1% on "Z" | ₹36.45 |
| Cost of 1.00 quintal | ₹3,681.92 |
| Cost of 1.00 kg | ₹36.82 |
| Say | ₹36.80 |