Variant 1
Extra for scrapping, cleaning and straightening reinforcement from R.C.C. or R.B. work.
DSR rate₹9.05as per item analysis
- Item code
- 15.6
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 117
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 10 Nos | |||||
| 6 metres long 16 mm dia bars @ 1.58 kg/metre | |||||
| Total weight = 94.80 kg = 0.948 quintal | |||||
| LABOUR | |||||
| 0103 | Blacksmith 2nd class | day | 0.25 | ₹816.00 | ₹204.00 |
| 0114 | Beldar | day | 0.5 | ₹736.00 | ₹368.00 |
| 9999 | Sundries | L.S. | 13.39 | ₹2.27 | ₹30.40 |
Rate build-up
| TOTAL | ₹602.40 |
| Add 1 % Water charges on "W" | ₹6.02 |
| TOTAL | ₹608.42 |
| Add GST on "X" (multiplying factor 0.2127) | ₹129.41 |
| TOTAL | ₹737.83 |
| Add 15% CPOH on "Y" | ₹110.67 |
| TOTAL | ₹848.50 |
| Add Cess @ 1% on "Z" | ₹8.49 |
| Cost of 94.80 kg | ₹856.99 |
| Cost of 1.00 kg | ₹9.04 |
| Say | ₹9.05 |