CPWD DSR item 15.7.1 rate analysis

Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. In mud mortar

Published rate₹704.90DSR 2023
Rate analysis

Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge.

DSR rate₹704.90as per item analysis

In mud mortar

Item code
15.7.1
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
138

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 1 cum
LABOUR
0114 Beldar day 0.3 ₹736.00 ₹220.80
0115 Coolie day 0.37 ₹736.00 ₹272.32
9999 Sundries L.S. 1.04 ₹2.27 ₹2.36

Rate build-up

TOTAL ₹495.48
Add 1 % Water charges on "W" ₹4.95
TOTAL ₹500.43
Add GST on "X" (multiplying factor 0.2127) ₹106.44
TOTAL ₹606.87
Add 15% CPOH on "Y" ₹91.03
TOTAL ₹697.90
Add Cess @ 1% on "Z" ₹6.98
Cost of 1.00 cum ₹704.88
Say ₹704.90