DSR 2023 · SH 15 · DISMANTLING

CPWD DSR item 15.7.2 rate analysis

Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. In lime mortar with old mughal bricks

Published rate₹1,783.35DSR 2023
Rate analysis

Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge.

DSR rate₹1,783.35as per item analysis

In lime mortar with old mughal bricks

Item code
15.7.2
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
138

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 1 cum
LABOUR
0114 Beldar day 1.24 ₹736.00 ₹912.64
0115 Coolie day 0.46 ₹736.00 ₹338.56
9999 Sundries L.S. 1.04 ₹2.27 ₹2.36

Rate build-up

TOTAL ₹1,253.56
Add 1 % Water charges on "W" ₹12.54
TOTAL ₹1,266.10
Add GST on "X" (multiplying factor 0.2127) ₹269.30
TOTAL ₹1,535.40
Add 15% CPOH on "Y" ₹230.31
TOTAL ₹1,765.71
Add Cess @ 1% on "Z" ₹17.66
Cost of 1.00 cum ₹1,783.37
Say ₹1,783.35

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook