Rate analysis
Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge.
DSR rate₹851.50as per item analysis
In lime mortar
- Item code
- 15.7.3
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 138
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 1 cum | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 0.44 | ₹736.00 | ₹323.84 |
| 0115 | Coolie | day | 0.37 | ₹736.00 | ₹272.32 |
| 9999 | Sundries | L.S. | 1.04 | ₹2.27 | ₹2.36 |
Rate build-up
| TOTAL | ₹598.52 |
| Add 1 % Water charges on "W" | ₹5.99 |
| TOTAL | ₹604.51 |
| Add GST on "X" (multiplying factor 0.2127) | ₹128.58 |
| TOTAL | ₹733.09 |
| Add 15% CPOH on "Y" | ₹109.96 |
| TOTAL | ₹843.05 |
| Add Cess @ 1% on "Z" | ₹8.43 |
| Cost of 1.00 cum | ₹851.48 |
| Say | ₹851.50 |