DSR 2023 · SH 15 · DISMANTLING

CPWD DSR item 15.7.3 rate analysis

Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. In lime mortar

Published rate₹851.50DSR 2023
Rate analysis

Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge.

DSR rate₹851.50as per item analysis

In lime mortar

Item code
15.7.3
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
138

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 1 cum
LABOUR
0114 Beldar day 0.44 ₹736.00 ₹323.84
0115 Coolie day 0.37 ₹736.00 ₹272.32
9999 Sundries L.S. 1.04 ₹2.27 ₹2.36

Rate build-up

TOTAL ₹598.52
Add 1 % Water charges on "W" ₹5.99
TOTAL ₹604.51
Add GST on "X" (multiplying factor 0.2127) ₹128.58
TOTAL ₹733.09
Add 15% CPOH on "Y" ₹109.96
TOTAL ₹843.05
Add Cess @ 1% on "Z" ₹8.43
Cost of 1.00 cum ₹851.48
Say ₹851.50

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook