DSR 2023 · SH 15 · DISMANTLING

CPWD DSR item 15.7.4 rate analysis

Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. In cement mortar

Published rate₹2,060.20DSR 2023
Rate analysis

Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge.

DSR rate₹2,060.20as per item analysis

In cement mortar

Item code
15.7.4
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
138

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 1 cum
LABOUR
0114 Beldar day 1.06 ₹736.00 ₹780.16
0115 Coolie day 0.9 ₹736.00 ₹662.40
9999 Sundries L.S. 2.47 ₹2.27 ₹5.61

Rate build-up

TOTAL ₹1,448.17
Add 1 % Water charges on "W" ₹14.48
TOTAL ₹1,462.65
Add GST on "X" (multiplying factor 0.2127) ₹311.11
TOTAL ₹1,773.76
Add 15% CPOH on "Y" ₹266.06
TOTAL ₹2,039.82
Add Cess @ 1% on "Z" ₹20.40
Cost of 1.00 cum ₹2,060.22
Say ₹2,060.20