DSR 2023 · SH 15 · DISMANTLING

CPWD DSR item 15.8.1 rate analysis

Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured): From brick work in mud mortar

Published rate₹4,658.45DSR 2023
Rate analysis

Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured):

DSR rate₹4,658.45as per item analysis

From brick work in mud mortar

Item code
15.8.1
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
211

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 1000 Nos
LABOUR
0114 Beldar day 2.4 ₹736.00 ₹1,766.40
0115 Coolie day 1.6 ₹736.00 ₹1,177.60
0124 Mason 2nd class day 0.4 ₹816.00 ₹326.40
9999 Sundries L.S. 1.82 ₹2.27 ₹4.13

Rate build-up

TOTAL ₹3,274.53
Add 1 % Water charges on "W" ₹32.75
TOTAL ₹3,307.28
Add GST on "X" (multiplying factor 0.2127) ₹703.46
TOTAL ₹4,010.74
Add 15% CPOH on "Y" ₹601.61
TOTAL ₹4,612.35
Add Cess @ 1% on "Z" ₹46.12
Cost of 1000 Nos ₹4,658.47
Say ₹4,658.45