Rate analysis
Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured):
DSR rate₹4,658.45as per item analysis
From brick work in mud mortar
- Item code
- 15.8.1
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 211
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 1000 Nos | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 2.4 | ₹736.00 | ₹1,766.40 |
| 0115 | Coolie | day | 1.6 | ₹736.00 | ₹1,177.60 |
| 0124 | Mason 2nd class | day | 0.4 | ₹816.00 | ₹326.40 |
| 9999 | Sundries | L.S. | 1.82 | ₹2.27 | ₹4.13 |
Rate build-up
| TOTAL | ₹3,274.53 |
| Add 1 % Water charges on "W" | ₹32.75 |
| TOTAL | ₹3,307.28 |
| Add GST on "X" (multiplying factor 0.2127) | ₹703.46 |
| TOTAL | ₹4,010.74 |
| Add 15% CPOH on "Y" | ₹601.61 |
| TOTAL | ₹4,612.35 |
| Add Cess @ 1% on "Z" | ₹46.12 |
| Cost of 1000 Nos | ₹4,658.47 |
| Say | ₹4,658.45 |