DSR 2023 · SH 15 · DISMANTLING

CPWD DSR item 15.10.2 rate analysis

In cement mortar

Published rate₹2,877.75DSR 2023
Rate analysis

In cement mortar

DSR rate₹2,877.75as per item analysis
Item code
15.10.2
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
325

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 1 cum
LABOUR
0114 Beldar day 1.55 ₹736.00 ₹1,140.80
0115 Coolie day 1.19 ₹736.00 ₹875.84
9999 Sundries L.S. 2.73 ₹2.27 ₹6.20

Rate build-up

TOTAL ₹2,022.84
Add 1 % Water charges on "W" ₹20.23
TOTAL ₹2,043.07
Add GST on "X" (multiplying factor 0.2127) ₹434.56
TOTAL ₹2,477.63
Add 15% CPOH on "Y" ₹371.64
TOTAL ₹2,849.27
Add Cess @ 1% on "Z" ₹28.49
Cost of 1.00 cum ₹2,877.76
Say ₹2,877.75

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook