Removing mortar from and cleaning stones and concrete articles (net quantity of stacks of cleaned materials will be measured): In lime mortar

Published rate₹478.55DSR 2023
Rate analysis

Removing mortar from and cleaning stones and concrete articles (net quantity of stacks of cleaned materials will be measured):

DSR rate₹478.55as per item analysis

In lime mortar

Item code
15.11.1
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
343

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 1 cum
LABOUR
0124 Mason 2nd class day 0.05 ₹816.00 ₹40.80
0114 Beldar day 0.2 ₹736.00 ₹147.20
0115 Coolie day 0.2 ₹736.00 ₹147.20
9999 Sundries L.S. 0.52 ₹2.27 ₹1.18

Rate build-up

TOTAL ₹336.38
Add 1 % Water charges on "W" ₹3.36
TOTAL ₹339.74
Add GST on "X" (multiplying factor 0.2127) ₹72.26
TOTAL ₹412.00
Add 15% CPOH on "Y" ₹61.80
TOTAL ₹473.80
Add Cess @ 1% on "Z" ₹4.74
Cost of 1.00 cum ₹478.54
Say ₹478.55