Removing mortar from and cleaning stones and concrete articles (net quantity of stacks of cleaned materials will be measured): In cement mortar

Published rate₹689.20DSR 2023
Rate analysis

Removing mortar from and cleaning stones and concrete articles (net quantity of stacks of cleaned materials will be measured):

DSR rate₹689.20as per item analysis

In cement mortar

Item code
15.11.2
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
343

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 1 cum
LABOUR
0124 Mason 2nd class day 0.05 ₹816.00 ₹40.80
0114 Beldar day 0.4 ₹736.00 ₹294.40
0115 Coolie day 0.2 ₹736.00 ₹147.20
9999 Sundries L.S. 0.91 ₹2.27 ₹2.07

Rate build-up

TOTAL ₹484.47
Add 1 % Water charges on "W" ₹4.84
TOTAL ₹489.31
Add GST on "X" (multiplying factor 0.2127) ₹104.08
TOTAL ₹593.39
Add 15% CPOH on "Y" ₹89.01
TOTAL ₹682.40
Add Cess @ 1% on "Z" ₹6.82
Cost of 1.00 cum ₹689.22