Rate analysis
Dismantling of cement concrete platform along with curtain walls and base concrete etc. including stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead :
DSR rate₹1,693.35as per item analysis
210 x 120 cm (outside to outside)
- Item code
- 15.55.2
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 1724
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for one platform | |||||
| Dismantling cement concrete 1:5:10 | |||||
| 5.80x0.35x0.12m =0.243cum | |||||
| 0.80x1.70x0.075m =0.102cum | |||||
| =0.345cum Say 0.35cum | |||||
| Dismantling brick work in cement mortar | |||||
| 5.80x0.20x0.30m =0.348cum | |||||
| 6.20x0.10x0.20m =0.124cum | |||||
| =0.472cum Say 0.47cum | |||||
| Dismantling 40 mm C.C. flooring 1:2:4 | |||||
| 1.90x1.00x0.04m =0.08cum | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 0.31 | ₹736.00 | ₹228.16 |
| 0115 | Coolie | day | 0.19 | ₹736.00 | ₹139.84 |
| 9999 | Sundries | L.S. | 0.65 | ₹2.27 | ₹1.48 |
| 0114 | Beldar | day | 0.5 | ₹736.00 | ₹368.00 |
| 0115 | Coolie | day | 0.42 | ₹736.00 | ₹309.12 |
| 9999 | Sundries | L.S. | 1.3 | ₹2.27 | ₹2.95 |
| 0114 | Beldar | day | 0.13 | ₹736.00 | ₹95.68 |
| 0115 | Coolie | day | 0.06 | ₹736.00 | ₹44.16 |
| 9999 | Sundries for scaffolding etc | L.S. | 0.39 | ₹2.27 | ₹0.89 |
Rate build-up
| TOTAL | ₹1,190.28 |
| Add 1 % Water charges on "W" | ₹11.90 |
| TOTAL | ₹1,202.18 |
| Add GST on "X" (multiplying factor 0.2127) | ₹255.70 |
| TOTAL | ₹1,457.88 |
| Add 15% CPOH on "Y" | ₹218.68 |
| TOTAL | ₹1,676.56 |
| Add Cess @ 1% on "Z" | ₹16.77 |
| Cost of each | ₹1,693.33 |
| Say | ₹1,693.35 |