DSR 2023 · SH 15 · DISMANTLING

CPWD DSR item 15.55.1 rate analysis

Dismantling of cement concrete platform along with curtain walls and base concrete etc. including stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead : 120 x 120 cm (outside to outside)

Published rate₹1,104.05DSR 2023
Rate analysis

Dismantling of cement concrete platform along with curtain walls and base concrete etc. including stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead :

DSR rate₹1,104.05as per item analysis

120 x 120 cm (outside to outside)

Item code
15.55.1
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
1724

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for one platform
Dismantling cement concrete 1:5:10
4.00x0.35x0.12m =0.168cum
0.80x0.80x0.075m =0.048cum
=0.216cum Say 0.22cum
Dismantling brick work in cement mortar
4.00x0.20x0.30m =0.24cum
4.00x0.10x0.20m =0.088cum
=0.328cum Say 0.33cum
Dismantling 40 mm C.C. flooring 1:2:4
1.00x1.00x0.04m =0.04cum
LABOUR
0114 Beldar day 0.19 ₹736.00 ₹139.84
0115 Coolie day 0.12 ₹736.00 ₹88.32
9999 Sundries L.S. 0.39 ₹2.27 ₹0.89
0114 Beldar day 0.35 ₹736.00 ₹257.60
0115 Coolie day 0.3 ₹736.00 ₹220.80
9999 Sundries L.S. 0.91 ₹2.27 ₹2.07
0114 Beldar day 0.06 ₹736.00 ₹44.16
0115 Coolie day 0.03 ₹736.00 ₹22.08
9999 Sundries for scaffolding etc L.S. 0.13 ₹2.27 ₹0.30

Rate build-up

TOTAL ₹776.06
Add 1 % Water charges on "W" ₹7.76
TOTAL ₹783.82
Add GST on "X" (multiplying factor 0.2127) ₹166.72
TOTAL ₹950.54
Add 15% CPOH on "Y" ₹142.58
TOTAL ₹1,093.12
Add Cess @ 1% on "Z" ₹10.93
Cost of each ₹1,104.05
Say ₹1,104.05

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook