Rate analysis
Dismantling of spindle fire hydrant including stacking of useful materials within 50 metres lead.
DSR rate₹726.35as per item analysis
- Item code
- 15.54
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 1705
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 10 Nos | |||||
| LABOUR | |||||
| 0116 | Fitter (grade 1) | day | 1.5 | ₹897.00 | ₹1,345.50 |
| 0117 | Assistant Fitter or 2nd class Fitter | day | 1 | ₹816.00 | ₹816.00 |
| 0114 | Beldar | day | 4 | ₹736.00 | ₹2,944.00 |
Rate build-up
| TOTAL | ₹5,105.50 |
| Add 1 % Water charges on "W" | ₹51.06 |
| TOTAL | ₹5,156.56 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,096.80 |
| TOTAL | ₹6,253.36 |
| Add 15% CPOH on "Y" | ₹938.00 |
| TOTAL | ₹7,191.36 |
| Add Cess @ 1% on "Z" | ₹71.91 |
| Cost of 10 Nos | ₹7,263.27 |
| Cost of each | ₹726.33 |
| Say | ₹726.35 |