Rate analysis
Dismantling tiled roofing with battens, boarding etc. complete including stacking of serviceable material and disposal of unserviceable material within 50 metres lead.
DSR rate₹209.90as per item analysis
- Item code
- 15.31
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 900
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 10 sqm | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 1.73 | ₹736.00 | ₹1,273.28 |
| 0115 | Coolie | day | 0.25 | ₹736.00 | ₹184.00 |
| 9999 | Sundries | L.S. | 8.06 | ₹2.27 | ₹18.30 |
Rate build-up
| TOTAL | ₹1,475.58 |
| Add 1 % Water charges on "W" | ₹14.76 |
| TOTAL | ₹1,490.34 |
| Add GST on "X" (multiplying factor 0.2127) | ₹317.00 |
| TOTAL | ₹1,807.34 |
| Add 15% CPOH on "Y" | ₹271.10 |
| TOTAL | ₹2,078.44 |
| Add Cess @ 1% on "Z" | ₹20.78 |
| Cost of 10.00 sqm | ₹2,099.22 |
| Cost of 1.00 sqm | ₹209.92 |
| Say | ₹209.90 |