Rate analysis
Dismantling stone slab roofing over wooden karries or R.C.C. battens (dismantling karries and battens to be paid for separately), including stacking of serviceable material and disposal of unserviceable material within 50 metres lead.
DSR rate₹2,664.65as per item analysis
- Item code
- 15.29
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 863
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 1 cum | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 1.77 | ₹736.00 | ₹1,302.72 |
| 0115 | Coolie | day | 0.75 | ₹736.00 | ₹552.00 |
| 9999 | Sundries | L.S. | 8.06 | ₹2.27 | ₹18.30 |
Rate build-up
| TOTAL | ₹1,873.02 |
| Add 1 % Water charges on "W" | ₹18.73 |
| TOTAL | ₹1,891.75 |
| Add GST on "X" (multiplying factor 0.2127) | ₹402.38 |
| TOTAL | ₹2,294.13 |
| Add 15% CPOH on "Y" | ₹344.12 |
| TOTAL | ₹2,638.25 |
| Add Cess @ 1% on "Z" | ₹26.38 |
| Cost of 1.00 cum | ₹2,664.63 |
| Say | ₹2,664.65 |