Published rate₹3,177.25DSR 2023
Rate analysis

Demolishing R.B. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in- charge.

DSR rate₹3,177.25as per item analysis
Item code
15.4
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
79

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 1 cum
LABOUR
0114 Beldar day 2.12 ₹736.00 ₹1,560.32
0115 Coolie day 0.9 ₹736.00 ₹662.40
9999 Sundries L.S. 4.68 ₹2.27 ₹10.62

Rate build-up

TOTAL ₹2,233.34
Add 1 % Water charges on "W" ₹22.33
TOTAL ₹2,255.67
Add GST on "X" (multiplying factor 0.2127) ₹479.78
TOTAL ₹2,735.45
Add 15% CPOH on "Y" ₹410.32
TOTAL ₹3,145.77
Add Cess @ 1% on "Z" ₹31.46
Cost of 1.00 cum ₹3,177.23
Say ₹3,177.25