Rate analysis
Extra for dismantling trusses, rafters, purlins etc. of steel work for every additional span of one metre or part thereof beyond 10 metres
DSR rate₹0.85as per item analysis
- Item code
- 15.2
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 652
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 1 quintal for every additional span of 1 metre beyond 10 metre | |||||
| LABOUR | |||||
| 0100 | Bandhani | day | 0.02 | ₹816.00 | ₹16.32 |
| 0114 | Beldar | day | 0.06 | ₹736.00 | ₹44.16 |
| 9999 | Sundries | L.S. | 0.39 | ₹2.27 | ₹0.89 |
Rate build-up
| TOTAL | ₹61.37 |
| Add 1 % Water charges on "W" | ₹0.61 |
| TOTAL | ₹61.98 |
| Add GST on "X" (multiplying factor 0.2127) | ₹13.18 |
| TOTAL | ₹75.16 |
| Add 15% CPOH on "Y" | ₹11.27 |
| TOTAL | ₹86.43 |
| Add Cess @ 1% on "Z" | ₹0.86 |
| Cost of 1.00 quintal per metre span | ₹87.29 |
| Cost of 1.00 kg per metre span | ₹0.87 |
| Say | ₹0.85 |