DSR 2023 · SH 15 · DISMANTLING

CPWD DSR item 15.23.2 rate analysis

Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres lead. For thickness of tiles above 25 mm and up to 40 mm

Published rate₹113.35DSR 2023
Rate analysis

Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres lead.

DSR rate₹113.35as per item analysis

For thickness of tiles above 25 mm and up to 40 mm

Item code
15.23.2
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
708

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 10 sqm
LABOUR
0124 Mason 2nd class day 0.59 ₹816.00 ₹481.44
0114 Beldar day 0.18 ₹736.00 ₹132.48
0115 Coolie day 0.24 ₹736.00 ₹176.64
9999 Sundries L.S. 2.73 ₹2.27 ₹6.20

Rate build-up

TOTAL ₹796.76
Add 1 % Water charges on "W" ₹7.97
TOTAL ₹804.73
Add GST on "X" (multiplying factor 0.2127) ₹171.17
TOTAL ₹975.90
Add 15% CPOH on "Y" ₹146.39
TOTAL ₹1,122.29
Add Cess @ 1% on "Z" ₹11.22
Cost of 10.00 sqm ₹1,133.51
Cost of 1.00 sqm ₹113.35
Say ₹113.35

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook