Rate analysis
Dismantling cement asbestos or other hard board ceiling or partition walls including stacking of serviceable materials and disposal of unserviceable materials within 50 metres lead.
DSR rate₹56.35as per item analysis
- Item code
- 15.41
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 1174
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 10 sqm. | |||||
| LABOUR | |||||
| 0112 | Carpenter 2nd class | day | 0.2 | ₹816.00 | ₹163.20 |
| 0114 | Beldar | day | 0.3 | ₹736.00 | ₹220.80 |
| 9999 | Sundries | L.S. | 5.33 | ₹2.27 | ₹12.10 |
Rate build-up
| TOTAL | ₹396.10 |
| Add 1 % Water charges on "W" | ₹3.96 |
| TOTAL | ₹400.06 |
| Add GST on "X" (multiplying factor 0.2127) | ₹85.09 |
| TOTAL | ₹485.15 |
| Add 15% CPOH on "Y" | ₹72.77 |
| TOTAL | ₹557.92 |
| Add Cess @ 1% on "Z" | ₹5.58 |
| Cost of 10.00 sqm. | ₹563.50 |
| Cost of 1.00 sqm. | ₹56.35 |
| Say | ₹56.35 |