Rate analysis
Dismantling and stacking within 50 metres lead, fencing posts or struts including all earth work and dismantling of concrete etc. in base of:
DSR rate₹230.90as per item analysis
T' or 'L' iron or pipe
- Item code
- 15.34.1
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 956
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for each | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 0.107 | ₹736.00 | ₹78.75 |
| 0115 | Coolie | day | 0.067 | ₹736.00 | ₹49.31 |
| 9999 | Excavation, transporting and stacking the posts to the required place within 50 metres lead, refilling the pit and dressing the same | L.S. | 0.26 | ₹2.27 | ₹0.59 |
| 9999 | Extra for lifting of R.C.C. posts being heavier than L iron and cleaning the posts of stacking concrete | L.S. | 13.39 | ₹2.27 | ₹30.40 |
| 9999 | Sundries | L.S. | 1.43 | ₹2.27 | ₹3.25 |
Rate build-up
| TOTAL | ₹162.30 |
| Add 1 % Water charges on "W" | ₹1.62 |
| TOTAL | ₹163.92 |
| Add GST on "X" (multiplying factor 0.2127) | ₹34.87 |
| TOTAL | ₹198.79 |
| Add 15% CPOH on "Y" | ₹29.82 |
| TOTAL | ₹228.61 |
| Add Cess @ 1% on "Z" | ₹2.29 |
| Cost of each | ₹230.90 |
| Say | ₹230.90 |